Greenfield installations
Greenfield installation: delivery governance from design to handover
One overview of schedule confidence, test readiness and open risks before factory acceptance starts.
Illustrative example · fictional data
The situation
A fictional greenfield production line is being built in several packages. The client wants one clear overview of schedule confidence, test readiness and open risks before FAT starts.
Project phase
Requirements
Done
Procurement
Done
Installation
In progress
FAT
Open
SAT
Open
Handover
Open
Delivery confidence (0–100)
- Schedule58
- Cost control74
- Documentation61
- Test readiness (FAT/SAT)45
- Handover preparation52
Findings
1. High
FAT scope is not yet agreed with the supplier
Acceptance criteria exist only as a draft. Without a signed scope, a failed test cannot be judged objectively.
2. Medium
Progress is reported by package, not by system
Packages can be 90% complete while no system is ready to test. Reporting per system shows real test readiness.
3. Medium
Spare parts and training are not yet planned
Both are usually discovered at start-up, when changing them is expensive.
4. Low
Punch list has no agreed categories
Without categories, minor items compete with start-up blockers for attention.
Action plan
Quick wins
- Agree FAT scope and acceptance criteria in writing.
- Define punch-list categories (A, B, C).
Medium effort
- Report progress per system, so test readiness is visible.
Higher effort
- Plan spare parts, training and operator documentation as part of the handover scope.
Risk register
Likelihood →
Impact →
- 1
FAT delayed by unclear scope Score 16 (4×4)
Mitigation: Sign off scope and criteria before the FAT date is fixed.
- 2
Late equipment delivery Score 12 (3×4)
Mitigation: Weekly supplier status with an escalation route.
- 3
Operators not trained at start-up Score 9 (3×3)
Mitigation: Schedule training against SAT, not against handover.
- 4
Documentation gaps found at SAT Score 12 (4×3)
Mitigation: Check the document list per system two weeks before SAT.
Recommendation
Proceed to FAT only after scope and criteria are signed off. Switch progress reporting to systems and review again two weeks before SAT.
What you receive
- One-page delivery dashboard per phase
- FAT and SAT scope with acceptance criteria
- Risk register (likelihood × impact) with mitigation
- Handover checklist owned by the future operator